The first Robbins Crossover TBM to be used in the United States is assembled, factory tested and ready for its work on a short but complex 1.89km (1.17 mile) interceptor sewer tunnel project in Akron, Ohio.
With a diameter of 9.26m (30.4ft) the machine includes features of both EPB and hard rock single shield TBM types to work in both soft ground and open hard rock modes. It will launch from a 12m deep portal site and excavate the first 68m (226ft) in soft ground, transitioning to a 183m (600ft) zone of partial face shale before switching to hard-rock mode for the remainder of the drive in full face shale. Continuous and systematic probe drilling, using two probe drills on the machine, will determine which mode the TBM should be in.
The machine was initially unveiled and factory tested at the Robbins Solon, Ohio headquarters on May 25 2017 before being shipped 40km south to the construction job site. Those present at the unveiling included Akron Mayor Daniel Horrigan, Robbins Chief Engineer Dennis Ofiara, and David Chastka, Project Engineer for the engaged Kenny-Obayashi JV contractor.
Additional aspects of the machine include a versatile cutterhead that is configured with a combination of disc cutters and sacrificial rippers for both the short soft ground section and the longer section in hard rock. The sacrificial rippers will be used in case a cutter becomes blocked. The required rolling torque of the disc cutters has been reduced by 25% to encourage smooth rotation in soft ground. The motors of the Crossover XRE machine have been reworked from an original EPB configuration to permit higher motor speed at reduced torque for the open mode segments of the drive.
Muck extraction from the excavation chamber will be achieved via a durable screw conveyor, the first flight of which is covered with welded-in wear plates. The auger shaft is lined with hard facing in a crosshatch pattern, while the screw conveyor casing has been similarly lined in wear plates and hard facing. A wear monitoring plan has been prepared for the entire drive in order to maximize efficiency in the section of more abrasive rock. Muck will be transported out of the tunnel using a Robbins continuous conveyor system, the 100th such conveyor system supplied by Robbins for operation behind a TBM.
Many components of the machine were fabricated locally in the northest Ohio area, creating jobs with local sub-suppliers, explained Robbins Project Manager Pablo Salazar. with sub-suppliers, as well as in our own shop.”
The TBM will be shipped in truckloads to the jobsite with the large cutterhead shipped in four pieces. “The entire process of assembly has allowed the contractor to follow closely the testing of the machine, so they are familiar with the TBM at this point,” said Salazar. “At the jobsite and during the drive, we will provide support personnel and supply of spare parts.” Jobsite supervisors from Robbins will help with TBM assembly and excavation for at least the first 1,000m (3,280ft) of boring, which is scheduled to begin in August of this year.
The Ohio Canal interceptor tunnel for the City of Akron will provide control of combined sewer overflows at several regulators in the downtown Akron area. In addition to the 1.89km conveyance and storage tunnel, the mandated project by the US Environmental Protection Agency (EPA) includes drop shafts, diversion structures, consolidation sewers, and related structures. The EPA consent decree specifies that the tunnel must be operational by December 31, 2018.
In Brief
|
|