With the Northgate and East Link light rail extensions in Seattle on schedule for completion in 2021 and 2023, the city is planning its next phase of light rail expansion (Fig 1). Known as ST3 and following voter approval of funding in 2016, the programme includes plans for a significant new underground section on the planned West Seattle-Ballard Line, which will run from Alaska Junction in the southwest, through the Chinatown/International District and under the city centre to Ballard in the north.
The West Seattle-Ballard Line will total about 12 miles (19km) of underground and surface alignments with nine new stations (Fig 2). The exact route is yet to be confirmed and “significantly, all the options currently under review in downtown Seattle are for underground alignments,” David Jackson of Sound Transit told TunnelTalk. “There are further reaches of underground alignment being considered near the north and south terminals of the line. Some of these underground options would require additional funding beyond what has already been approved by voters,” he added.
Construction of the West Seattle-Ballard line is to be in two phases for a start of services scheduled for 2030 on the West Seattle element and 2035 for the Ballard link. “The project is in the environmental impact statement study period at present and it is from these studies that the final routes will be decided,” Jackson continued. The Sound Transit Board preferred route and several alternatives form part of the draft environmental impact study, which is expected to be released for public review and comment in January 2021. Design work is expected to progress between 2022 and 2026 with construction beginning in 2025 on the West Seattle element and 2027 on the Ballard section.
The remaining more than 50 miles (80km) of light rail included in the ST3 programme is likely to be at-grade or elevated with the “choice of guideway reflective of the service area of the project”, said Jackson. The West Seattle-Ballard route will run under the downtown area of the city, where space is at a premium, while the remaining routes will be constructed in more suburban locations, where space allows surface development. The ST3 programme is scheduled to be complete by 2041.
Work on the 2,235ft (681m) underground Belleview section of the 14 mile (22.5km) East Link to serve the communities of Mercer Island, Bellevue and Redmond, is ongoing by contractor Guy F Anderson and design engineer Mott McDonald and construction managers McMillen Jacobs Associates (Figs 3 and 4). Running through glacial till and outwash gravel under downtown Belleview, SEM sequential excavation method construction has been completed using a Liebherr 950 excavator. The alignment includes a 250ft cut-and-cover structure.
SEM progressed on a full top heading, bench and invert sequence through the first half of the alignment, which ran through more competent glacial till. It then changed to a more controlled excavation through the more complex outwash material in six stages dividing the heading with a single sidewall drift.
The 38ft o.d. excavation is supported with an initial 1ft thick macro-synthetic fibre reinforced (MSFR) shotcrete and lined with a 1ft thick cast-in-place concrete lining to a finished i.d. of 34ft, with both spray waterproofing and membrane waterproofing in between applied in different sections.
Lattice girders supplied by Jenmar were installed and the macro-synthetic fibre was supplied by Barchip. A Normet Spraymec 8100 robot applied the shotcrete and the spray waterproofing supplied by Mapei. Sheet membrane was supplied by Grace and applied by subcontractor FD Thomas.
With a budget of US$121 million for the underground work within the project total of $1.6 billion, excavation is complete, despite a leaking storm drain causing difficulty with installation of the initial lining, and finishing works are underway. The Belleview alignment will also form part of the planned 11.4 mile South Kirtland-Issaquah Link of the ST3 programme, which is currently scheduled to go into service in 2041.
In addition to the Belleview tunnel, the route includes two additional underground sections that will run through the existing Mount Baker and Mercer Island tunnels. Previously used for road traffic, these two alignments have been converted for use by light rail.
Running through some of the most congested neighbourhoods of the Seattle region, the 4.3 mile (7km) Northgate Link includes twin 3.5 x 22ft o.d. TBM-bored alignments lined with segments to 18ft 10in (Fig 6). Excavation was completed in 2016 using refurbished EPBMs from Hitachi Zosen and Robbins and was troubled when the latter machine broke down during its second of three drives. The Hitachi Zosen machine completed the third drive of the parallel tunnel to achieve final TBM breakthrough some five months later than planned. The breakdown of the TBM is currently subject to legal proceedings.
In addition to the challenges of geology and equipment, surface noise and vibration had to be carefully controlled during excavation of Northgate alignments, as the line runs under the University of Washington and residential neighbourhoods. Don Davis, Project Director for the Northgate Link Extension, told TunnelTalk that the concern required schedule constraints on how long the TBMs could work under the campus at one time.
When operational, vibration will be controlled by floating slabs of extra-dense concrete, each of which sits on a custom-built rubber pad. It is the first time the technology has been applied on a light rail network in the USA.
The project also included excavation of 23 cross passages, of which 11 required ground freezing support. Five of these used vertical drilling from the surface, while horizontal drilling from within the completed tunnel was used at six locations where ground conditions, including unexpectedly permeable soil and unstable running silt, made the original dewatering plans infeasible. The remaining 12 cross passages were supported by dewatering and local ground control. At 17ft wide x 18ft high and varying from 15ft to 25ft in length, excavation of the cross passages was by SEM on 3ft headings and applying shotcrete and lattice girders. Ground freezing was used also to create a support canopy for TBM breakthrough into the University District Station.
The Northgate Link also includes construction of two new underground stations at University District and Roosevelt under a separate contract by Hoffman Construction.
With a total taxpayer budget of $1.99 billion with US$1.4 billion for construction costs including $500 million for the underground element, work has so far been completed on schedule and within budget said Davis. Construction was managed by Jacobs Engineering, with design by McMillen Jacobs Associates.
|
|