Highways England has launched an 18-month procurement process to find potential contractors and tunnel specialists for the A303 Amesbury to Berwick Down scheme, which passes the World Heritage Site of Stonehenge. The company, responsible for the major A roads and motorways in England, has published its contract notice in the Official Journal of the European Union (OJEU) this week.
The proposed upgrade includes an approximately 3.3km-long twin-bore tunnel underneath the World Heritage Site. This is longer than the 2.9km tunnel previously proposed – a result of optimising the locations of the tunnel entrances to protect heritage and to best integrate the scheme into the surrounding landscape. The tunnel will closely follow the existing A303 route, but a further 50m away from the Stonehenge monument in order to avoid important archaeological sites, and to avoid intruding on views of the setting sun from Stonehenge during the winter solstice.
Highways England Project Director Derek Parody said: “We expect this scheme to be of interest to some of the best construction companies in the world, that want to be part of delivering this transformational project – a scheme that will not only unlock congestion along this vital A303 route, conserve and enhance the outstanding universal value of the World Heritage Site, but also benefit the local and regional economy by providing skills and job opportunities for businesses large and small.”
The OJEU contract notice covers the £1.25 billion main works contract for the construction of the civil, structural, mechanical, electrical and technology components of the tunnel, including the tunnel boring machine, along with the approach roadworks and structures, and the environmental components of the scheme.
The procurement process has started while the Development Consent Order examination continues to progress, in order to be able to start construction on schedule in 2021, providing planning consent is granted. The procurement model is through competitive dialogue, allowing a period of design development and dialogue during the tender phase, when solutions are developed and tested for compliance with Development Consent Order requirements prior to awarding a contract.
This approach allows greater flexibility, with the appointed team able to start work soon after the contract is awarded. Contracts for enabling preliminary work will be procured separately, as part of the total £1.7 billion capital cost of the scheme. Highways England expect the main construction works to start in 2021 and continue for approximately five years until 2026.
The UK Government this week accounted commitment to construction of a 2.9km twin-tube tunnel as part of a 13km upgrade of the A303 road from two lanes of bi-directional traffic to a four lane dual carriageway to eliminate a major traffic bottleneck on the four-lane east-west route in southern England and protect the World Heritage site of the ancient Stonehenge monument.
In announcing a new preferred route for the estimated £1.6 billion upgrading bypass, Secretary of State for Transport Chris Grayling brought to a close a period of public consultation that the government was forced to conduct to re-examine a previous route that drew fierce opposition from the general public, commentators and UNESCO which lists sites of World Heritage.
The most significant improvements, according to a statement by Highways England, the project owner, include a change to the route through the western half of the World Heritage site and to the location of the western tunnel portal with both now closer to the line of the existing A303 than they were before the consultation.
The preferred route, it states, avoids many important archaeological sites, including newly-discovered barrows just to the east of another regional road, the A360 and avoids the road intruding on the view of the setting sun from Stonehenge during the winter solstice.
Upgrading the A303 between Amesbury and Berwick Down and through the new tunnel will improve journeys on a proposed Expressway to the South West of the UK, ease serious congestion in the area and through the village of Winterbourne Stoke and enhance the setting of Stonehenge by reconnecting it with its surrounding landscape and removing the sight and sound of traffic.
Table 1. Stonehenge tunnel timeline (1995-2021) | ||||||
1995 | First concrete proposal to tunnel A303 at Stonehenge is advanced by a Planning Conference, which recommends a 4km bored tunnel alignment. | |||||
1996 | 4km tunnel dropped on cost grounds | |||||
1999 | UK Government publishes plans for a 2.1km cut-and-cover tunnel, but National Trust objects | |||||
2002 | New plans for a 2.1km TBM-bored tunnel announced by UK Government | |||||
2002 | Balfour Beatty win £125 million ECI contract to develop a 12.5km upgrade to A303 including a 2.1km bored tunnel, beating off bids by Amec/Alfred McAlpine; Mowlem/Morgan Est; Robert McAlpine/Buoygues; and Skanska. Design team of Halcrow/Gifford appointed | |||||
2004 | Public Inquiry passes 2.1km bored tunnel scheme. Cost now estimated at £192 million (2003 prices) | |||||
July 2005 | Spiralling costs force the Government to announce a review of the project and look at alternatives | |||||
Oct 2005 | Cross-government steering group formed to review the costs of the 2.1km tunnel scheme passed at public inquiry, cost out alternatives, and launch a public consultation on 5 options, including a cut-and-cover tunnel | |||||
Jan 2006 | Public consultation begins on 5 options, based on the A303 Stonehenge Improvement Scheme Review (Stage 1), which now costs the tunnel scheme at £510 million | |||||
July 2006 | A303 Stonehenge Improvement Scheme Review (Stage 2) published by Highways Agency/ Balfour Beatty/ Costain/ Halcrow/ Gifford | |||||
Dec 2007 | On 6 December 2007, on cost grounds, the UK Department of Transport withdraws all orders and cancels the scheme and the interdepartmental review of alternative options. | |||||
2013 | A303 feasibility study announced as part of the Autumn Statement | |||||
2014 | Scheme included in the Roads Investment Strategy | |||||
2015-2016 | Route identification | |||||
12 January to 5 March 2017 | Non-statutory consultation on route options | |||||
September 2017 | Announcement of preferred route | |||||
Early 2018 | Statutory consultation on proposed scheme | |||||
Late 2018 | Submit planning application | |||||
2021 (TBC) | Start on site |
Following the announcement by the Department of Transport, Highways England is developing a more detailed proposal of the preferred route for another round of public comment, as required by the Planning Act 2008, before the final scheme is submitted to Government for development consent. If all goes according to its plan, Highways England aims to carry out the next round of consultation in early 2018 and start construction on the new road and its tunnel in 2021.
Upgrade of the A303 has been particularly sensitive and under planning since 1989 (Table 1). Between Amesbury and Berwick Down, the road passes 165m from Stonehenge with some 24,000 vehicles using the stretch of road daily, twice as much as the single carriageway was designed for. The road and traffic can be seen and heard from the Stonehenge monument, is a high accident rate blackspot and creates high levels of air pollution.
Previous efforts to advance the project have been defeated by public opposition and costs. Given the different routes explored in the past, the Government now believes it has adopted an acceptable alignment and has made money available to move forward. The project however remains controversial with leading personalities in the UK calling the current improved route and upgrade plan "the most brutal intrusion into the Stone Age landscape ever" and saying that the project needed a "complete re-think, not a minor tweak".
|
|