Global mining company Anglo American is in advanced discussions with Sirius Minerals over a potential takeover, offering a lifeline to its UK potash mine project, the future of which was uncertain after failing to raise the finance it required from bond investors at the end of 2019.
The proposed offer price of 5.5 pence per share values the share capital of Sirius at about £386 million, representing a 34.1% premium to the closing price of 4.1 pence per share on 7 January 2020, the last business day prior to the announcement.
The proposal follows the announcement in September 2019 that Sirius was undertaking a strategic review to assess the development plan for its Woodsmith polyhalite mine project and an appropriate financing structure to provide relevant funding. Sirius also announced that the review would include a process to seek a strategic partner in the project.
Sirius has progressed the project to an advanced stage, with construction now underway for more than two years. A significant amount of further financing is required to develop and commission the operation, which has proven challenging to procure on an economic basis. Anglo American has the resources and capabilities to help build on the achievements of the Sirius team. In a statement, Anglo American said it had identified the project as of interest some time ago, due to the quality of the underlying asset in terms of scale, resource life, operating cost profile and the nature and quality of the product.
The takeover would mark a return to fertiliser mining for Anglo American and provide certainty to Sirius shareholders as well as to its employees and customers.
Should an offer be successful, development work during the first two years would be broadly in line with the revised development plan by Sirius, with Anglo American updating the development timeline, optimising mine design and ensuring appropriate integration with its own operating standards and practices.
A statement from Sirius said that, subject to the successful outcome of ongoing discussions, the Board expects to be able to recommend a firm offer to its shareholders. Anglo American is now required to announce by 5 February 2020 if it intends to make a formal offer for Sirius.
Construction continues at Woodsmith Mine, despite a six month financial deadline now hanging over the project. Project owner, Sirius Minerals, has announced that, as a result of global market conditions, plus the political environment and ongoing uncertainty surrounding Brexit in the UK, raising the finance it requires from bond investors is now unlikely. The scope of construction activities on the project will now be adjusted, while the company undertakes a strategic review of its options.
Sirius secured a commitment letter with global financial provider JP Morgan in relation to a US$2.5 billion rolling credit facility (RCF) in April 2019, drawdown of which was subject to a number of conditions, the most significant of which was the successful issuance of US$500 million of senior secured notes. Satisfaction of the RCF conditions would also have given Sirius unrestricted access to the proceeds of the US$400 million of new convertible loans that were issued in May 2019, which are reported as restricted cash at 30 June 2019.
On 16 September 2019 the company Directors concluded that it was unlikely that it would be possible to complete the financing to satisfy the terms of the RCF commitment letter before it expires at the end of October. The company therefore intends to terminate the RCF commitment letter and to repay the proceeds of the $400 million escrow loans to loanholders as required.
At the same time, the decision has been taken to reduce the pace of development to focus on key areas of the project and provide a period of up to six months to review all available options for moving forward. Current cash flow forecasts indicate that it expects to have sufficient liquidity to continue to operate and meet its liabilities as they fall due until at least March 2020.
Meanwhile, construction to date has progressed in line with 2019 milestones at each of several construction sites.
In June 2019, drives 2 and 3 of the mineral transport system (MTS) were awarded to Strabag Tunnelling expanding its current involvement to a €1 billion contract to construct the remaining 24km of the 37km MTS, between the shaft at Lockwood Beck and the Woodsmith Mine. Strabag was contracted to the project in early 2018 and has started design and excavation of the Drive 1 contract, a 13km section from the tunnel portal at Wilton to Lockwood Beck.
The MTS is being excavated at a depth of 360m entirely within the essentially dry Redcar Mudstone, which extends from Woodsmith Mine to Teesside. Its alignment avoids water-bearing rock and abandoned mine workings, which overlay the Redcar Mudstone. The first TBM launched from Wilton, Teesside, in April 2019 and has advanced ahead of expectations. According to Sirius, Drive 1 has advanced 1.2km and is more than two months ahead of schedule, having cleared the Wilton International site boundary and passed under all the neighbouring industrial infrastructure towards Lockwood Beck. The 6m diameter Herrenknecht TBM is now averaging 17m/day, including planned technical stops and despite the relatively difficult shallow ground that exists through the first 3km of the tunnel. The average advance rate is expected to increase as the TBM exits the shallow alignment, allowing the machine to run at higher cutting speeds and with fewer interventions.
Two further machines were due to be launched from Woodsmith Mine and Lockwood Beck in early 2020 to complete the remaining 24km of the 6m i.d. tunnel. The faster than expected advance rates experienced on Drive 1, however, could remove the need for the planned TBM2 from Lockwood Beck, enabling Drive 1 to continue through Lockwood Beck to connect with Drive 3 TBM from Woodsmith Mine (Fig 1).
The 360m deep intermediate access shaft at Lockwood Beck has been excavated and lined to 51m deep. A grouting process has now commenced to prepare the ground ahead of the main shaft sinking to depth using a drill+blast Galloway. The temporary headframe is being erected and construction of the winder house has progressed on schedule. These operations are expected to complete in early 2020. Should TBM2 still be required, shaft bottom works will be undertaken before the shaft being handed over from shaft sinking contractor DMC to Strabag to begin construction of the launch cavern for Drive 2 towards Woodsmith Mine.
At the Woodsmith Mine site, a Herrenknecht vertical sinking machine (VSM) has excavated the first 115m of the 360m MTS shaft. This is claimed as a world record for this type of excavation, surpassing the previous record of 84m set in St Petersburg, Russia. The Galloway has now been installed and is being prepared to begin drill+blast excavation to the 360m depth. The temporary headframe and winder building are being erected on site and mechanical fit out is underway for start of excavation operations later in 2019. Once the shaft is complete, the Drive 3 TBM can be lowered to its base and assembled in a cavern to drive northwest towards Lockwood Beck (Fig 1).
The main production and service shafts at Woodsmith Mine are being constructed to a depth of 1,600m.
Excavation of the 35m diameter service shaft foreshaft to 45m was completed earlier in 2019, while excavation of the 6.75m i.d service shaft has reached its target depth of 118m using conventional excavation techniques, and a Herrenknecht shaft boring roadheader (SBR) will be used to excavate both shafts to their full depth. The first components of the machine began arriving on site in August 2019 and pre-assembly on the surface has commenced. Preparatory works are almost complete to enable construction of the SBR headframe and installation of the machine into the foreshaft, scheduled to be completed during December 2019. All major components of the permanent winder for the service shaft are also now in place. The temporary winders, which connect to the SBR during shaft construction to the 1,600m deep mining level, have also progressed on schedule.
Excavation of the 32m diameter production shaft foreshaft has progressed faster than expected and is almost at its target depth of 45m. The production shaft differs from the service shaft in that it has diaphragm walls installed to a depth of 120m. Excavation can therefore occur faster than seen in the service shaft. Along with excavation of the 6.75m i.d production shaft, construction of its permanent winder building is almost complete. It will hoist excavated muck to the surface from the shaft sinking SBR operations, and in full operation will hoist polyhalite for many decades to come.
Continuing development of the project beyond 31 March 2020 now depends on Sirius Minerals securing additional external financing.
|
|