Singapore DTSS Phase 2 detailed design 07 Jun 2018

TunnelTalk reporting

Detailed design of the deep sewer tunnels that comprise the Singapore DTSS Phase 2 is advancing ahead of work starting on excavation of the project’s main design-build tunnel contracts. Construction of the 50km of Phase 2 deep sewer tunnelling, running across the southern and western areas of Singapore, is awarded in five design-build contracts starting under Keppel Road at 35m below ground to the east and following the Ayer Rajah Expressway, under Tuas Bay to the Tuas water reclamation plant to the west (Fig 1 and Table 1).

Five construction packages of the Phase 2 deep tunnels
Five construction packages of the Phase 2 deep tunnels

All 50km of the new gravity-fed DTSS Phase 2 deep tunnels will be TBM excavated, using up to four TBMs per contract, and are segmentally lined with a secondary inner corrosive resistant lining. Each contract includes several temporary working shafts as well as permanent drop shafts and odour control structures.

Designers working with the contractors on the design-build contracts are considering designs for steel fibre and synthetic fibre-only reinforcement of the primary segmental lining and designs to meet the required inner corrosive resistant lining. Preliminary designs, prepared by the Black & Veatch and AECOM joint venture for the client, PUB, Singapore’s national water agency, require an inner corrosive resistant lining of microbiological-influenced corrosion- resistant concrete and an inner high density polyethylene (HDPE) protective lining to protect against corrosion, particularly from bacteria and other micro-organisms present and from gaseous fumes in the sewer environment (Fig 2 left).

Table 1. The five design-build contracts of the Phase 2 deep tunnels
Contract T-07 Contract Value: Sing $499 million
Ed Zublin AG (Singapore Branch) Length: 12km
From intersection of Jurong Pier Rd and AYE and follow AYE to Tuas Road plus link sewer Jalan Bahar/PIE junction to Benoi Road/AYE junction
Contract T-08 Contract Value: Sing $520 million
Penta-Ocean /Koh Brothers JV Length: 10km
Main sewer plus industrial water sewer from Jalan Buroh/Pioneer Road and Pioneer Section 1 before passing under Tuas Bay and terminating at Tuas water reclamation plant
Contract T-09 Contract Value: Sing $495 million
Leighton Contractors (Asia) Length: 8km
From intersection of Clementi Road and AYE to the intersection at Jurong Pier Road and AYE.
Contract T-10 Contract Value: Sing $340 million
Nishimatsu Length: 8km
From intersection of Portsdowns Road and AYE to the intersection of Clementi Road and AYE plus link sewer from Portsdown Road to Leedon Heights and intersection of Clementi Road and AYE to Clementi Road and West Coast Road
Contract T-11 Contract Value: Sing $472 million
Shanghai Tunnel Engineering Co Length: 12km
From Keppel Road to Portsdown Road plus link sewer from Sentosa to Warwick Road

For tunnel sections that cross under the sea on contracts T-08 and T-11, an additional waterproof membrane layer is to be installed between the segmental lining and the inner secondary lining to minimise any water ingress into the tunnel (Fig 2 right). These linings are required to extend the design life of the tunnels.

Corrosive resisting linings for the deep tunnels (left) and of the under sea reaches (right)
Corrosive resisting linings for the deep tunnels (left) and of the under sea reaches (right)
Fibre optic sensors will be embedded into the linings to monitor long-term design life during operation
Fibre optic sensors will be embedded into the linings to monitor long-term design life during operation

To monitor the design life of the new sewer system, the tunnels will also be fitted with a network of fibre optic sensors cast into the primary lining to enable remote monitoring of the long term structural integrity of the tunnels. This ability to monitor the structure will be critical also for when other construction works are underway in their vicinity, or during events of seismic activity.

Another innovation for the new DTSS Phase 2 system are gates within the permanent shafts that can be lowered into the deep tunnels to temporarily isolate the tunnels and provide dry environment for safe man access in the event that any repairs are required once in operation. During such repairs, the flow will bypass the isolated part of the tunnel via the link sewer network and rejoin the main tunnel downstream.

Among the detailed designers working with the contractors on the project, COWI in partnership with CPG Corporation are working for Leighton Asia, part of the CPB group, on contract T-09. The contract scope includes the design of an 8km-long section of sewer tunnel, with a 6m internal diameter, several shafts and the hydraulic structures and other facilities associated with the conveyance contract. It is the first win for the newly established COWI Singapore office.

Shaft gates will isolate flow should repairs be required during operation
Shaft gates will isolate flow should repairs be required during operation

COWI and CPG will work closely with Leighton Asia to devise solutions to various challenges on the contract, including investigating options to combine temporary work shafts, to minimise land take, and design ground improvement measures to reduce any impact on adjacent structures.

The deep tunnels in Phase 2 will connect to the existing deep tunnels in Phase 1, which serve the northern and eastern part of Singapore to create one seamless integrated system. DTSS Phase 1 was completed in 2008 and comprised construction of a 48km-long gravity-fed deep sewer tunnel to a new water reclamation plant at Changi (Fig 2).

In addition to the 50km of deep segmentally lined main tunnels, Phase 2 of the DTSS system includes another 50km of connection tunnels that are to be awarded as design-bid-build pipejacking contracts. Tenders for the first packages of these connection sewers have been invited and are due for return to PUB later in June 2018.

When Phase 2 is completed and in operation in 2025, the whole of Singapore will be served by the deep tunnel sewer system and its connection sewers directing all flow to three major water reclamation treatment plants that will recycle as much of the used water as possible and minimise the release of treated water to the sea outfalls.

References

Add your comment

Thank you for taking the time to share your thoughts and comments. You share in the wider tunnelling community, so please keep your comments smart and civil. Don't attack other readers personally, and keep your language professional.
In case of an error submitting Feedback, copy and send the text to Feedback@TunnelTalk.com
Name :


Date :

Email :


Phone No :

   Security Image Refresh
Enter the security code :
No spaces, case-sensitive