Doha Metro set for final project breakthrough 20 Aug 2016

Peter Kenyon, TunnelTalk

After 45 intermediate breakthroughs and 29 final machine breakthroughs, less than 1,000m of the initial 112,000m remains to be completed before TBM tunnelling is completed on the US$36 billion Doha Metro Phase 1 in Qatar. Barely 30 months have passed since Herrenknecht of Germany hosted the factory acceptance ceremony for the first five of 21 TBMs that were procured for the project by its owner QRail. TunnelTalk News Editor Peter Kenyon reports.

Final breakthrough on the ambitious Doha Metro project in Qatar is just weeks away, with only two of the total 21 Herrenknecht TBMs procured by the owner to complete the twin running tunnels still in operation.

Final Green Line breakthrough at Education City in March 2016
Final Green Line breakthrough at Education City in March 2016

Abdulla Ali Al-Mawlawi, for project owner QRail, told TunnelTalk that a final breakthrough ceremony at Terminal One of Hamad International Airport is planned for the end of September 2016. It will be preceded a few weeks earlier, at the beginning of September, with a penultimate breakthrough ceremony in the same location when the first of the last two operating machines completes its drive.

“Total tunnelling completed as of 1 August 2016, is 110,723m, with just 789.5m remaining to complete all underground excavation on Phase 1 of the Doha Metro project,” said Al-Mawlawi.

When the last machine emerges for completion of the 12km of twin-running tunnels that comprises the Red Line South as the last of four underground lines to be completed as part of Phase 1, some 112km of mechanised excavation will have been accomplished in the 26 months since the first TBM launch on the Red Line North in July 2014.

Fig 1. Four lines of the 72km Doha Metro Phase 1 (56km underground)
Fig 1. Four lines of the 72km Doha Metro Phase 1 (56km underground)
Fig 2. Phase 2 of the project, dotted line are underground sections
Fig 2. Phase 2 of the project, dotted line are underground sections

The 72km-long, 37-station first phase of the project (Fig 1), which set a world record for the number of TBMs working simultaneously on a single project when all 21 machines were in operation in August 2015, concentrates on construction of the central underground infrastructure at the heart of Doha. The project remains on schedule for the four-line system (Red Line North, Red Line South, Green Line and Gold Line) to be open and in service in 2020, a year later than originally scheduled but two years ahead of when the Qatari capital city is due to host the 2022 Soccer World Cup.

The metro network will be extended in Phase 2 with an all-underground circular line, the Blue Line (Fig 2) and an addition of underground, elevated and surface level extensions to all four of the Phase 1 lines that are currently under construction.

QRail remains uncommitted about the procurement schedule for Phase 2, which has a planning stage completion set in 2026. Al-Mawlawi confirmed to TunnelTalk that construction of the Blue Line is included in a second phase that will see the addition of 100 more stations and 40 more than previously announced, and adding: “Our focus for now in on Phase 1 so we will answer any Phase 2-related questions at a later stage.”

Table 1. Doha Metro underground contracts
Line Contractors US$ (bn) Award date Underground scope TBMs First TBM launch Final TBM breakthrough
Green PorrSaudi Binladen Group HBK Contracting 2.6 16 May 2013 2 x 16.6km
6 stations
6 Sept 2014 30 March 2016
Red Line (S) Qatari Diar/Vinci (QDVC JV***) GS Engineering Al-Darwish 2.05 16 May 2013 2 x 12.05km
5 stations
5 March 2014 [Expected Sept 2016]
Red Line (N) Salini-Impregilo SK Engineering Galfar Al Misnad 2.3 16 May 2013 2 x 11.3km
7 stations
4 19 July 2014 21 March 2016
Gold** Aktor Larsen & Tourbo Yapi Merkezi SFTA Al Jaber Engineering 3.3 20 Feb 2014 2 x 15km
13 stations
6 3 March 2015 19 May 2016
Main stations* Samsung C&T OHL Qatar Building Co. 1.4 25 May 2013 2 x stations: Msherieb Education City n/a n/a n/a
* Contract cancelled by QRail May 2016, balance of work awarded to Consolidated Contractors Group
** With Seli Overseas subcontracted to complete some of the tunnelling work
*** The QDVC JV also completed the underground excavations for the separate Lusail LRT system

In addition to the 56km of twin tube underground alignment, Phase 1 construction includes surface and elevated alignments that extend the Red Line North a further 6.5km as far north as the waterfront residential and commercial development of Lusail City for connection with the Lusail LRT which is also under construction. This new tram-based system, comprises four lines with 37 stations and 10km of the 38km network in double-track underground alignment.

Completion of Red Line North, March 2016
Completion of Red Line North, March 2016
Capturing the Red Line North breakthroughs

Further contracts for a 3km surface and elevated extension of the Green Line from Al Riffa westwards to the Al Rayyan Stadium, and for 6.5km of surface and elevated alignment out to Al Wakra at the southern end of the Red Line South, are nearing completion.

TBMs

For completion of the 112km of underground excavations, QRail, as owner of the project, procured all 21 EPBMs from Herrenknecht of Germany, with cutterhead diameters ranging from 7.05m to 7.11m. Selection of EPB technology was based on the expectation of a soft ground geology comprising Simsima Limestone and Midra Shale, with mechanised excavation proceeding at relatively shallow depths of an average 20m, and through a high groundwater table, especially in coastal locations.

Continuous conveyor mucking systems were supplied by H&E to some of the contracts with others, the other using rail-bound mucking systems. VMT provided systems to all TBMs for navigation, monitoring, communication and process data management. Emergency refuge chambers on board the 21 TBMs were supplied by MineARC and the segment moulds and handling equipment in the segmental lining casting yards were installed by Herrenknecht Formwork. For the contracts with continuous conveyor mucking systems, multi-service vehicles by MSD/Techni-Métal Systèmes provided in-tunnel transportation of men, materials and segments to the advancing TBM headings.

Acceptance of Red Line South TBMs in Feb 2014
Acceptance of Red Line South TBMs in Feb 2014

The first machines leave the Herrenknecht factory in Schwanau, were the five machines for the Red Line South (RLS), and event that with TunnelTalk attended and reported on in February 2014. The original program called for an early start on the Red Line South to facilitate addition of a 3.3km spur tunnel between Al Matar and Airport City within the contract. This spur, however, has not been built as planned, and will now form part of the Phase 2 Blue Line as originally envisaged.

By the time final project breakthrough is achieved, the TBMs used on the project will have recorded 45 intermediate breakthroughs, numerous TBM transfers, and 31 final machine breakthroughs. Al Mawlawi told TunnelTalk that as each machine completes its scheduled drives it is dismantled and all parts returned to the Herrenknecht maintenance facility in Doha for recycling or sale. New machines will therefore need to be procured for excavation of the Blue Line.

Program challenges

Progress across all four lines has been rapid, with the TBMs recording up to 30m/day at peak performance. On the Green Line a best daily rate of 60m was recorded by Porr of Austriawhile on the Red Line North a best daily advance rate of 42m was achieved by Salini Impregilo.­ The best daily rate of 43m and a project-best single machine monthly production rate of 920m was achieved on the Gold Line by tunnelling subcontractor Seli Overseas.

 Last Gold Line breakthrough by  subcontractor Seli Overseas (May 2016)
Last Gold Line breakthrough by subcontractor Seli Overseas (May 2016)

In spite of the immense achievements, the project has not been without its challenges. The most serious incident for the tunnelling works occurred in April last 2015 when progress on the Red Line South was stalled for three months following a flood event at al-Bidda Station on the Red Line North contract. The inundation of ground water and material through the screw conveyor when a technical fault prevented closure of the discharge gate, left the TBM completely submerged, and once recovered, repair required complete replacement of all electronic components and delivery of more than 1,000 spare parts from Germany.

As part of the contractual experience, earlier this year, in May, Spanish contractor OHL, as a partner in the Samsung/OHL/Qatar Building Company JV that was awarded the contract to build the two largest stations on the network at Education City and Msheireb, announced to the London Stock Exchange that QRail had terminated its contract on the grounds of “non-compliance of certain contractual obligations.” The contract has since been taken over by the Consolidated Contractors Group, with OHL now involved in a legal dispute with QRail.

TunnelTalk will continue to monitor progress as the project nears its final TBM breakthrough and on towards official opening of services on the network in 2020.

References

Add your comment

Thank you for taking the time to share your thoughts and comments. You share in the wider tunnelling community, so please keep your comments smart and civil. Don't attack other readers personally, and keep your language professional.
In case of an error submitting Feedback, copy and send the text to Feedback@TunnelTalk.com
Name :


Date :

Email :


Phone No :

   Security Image Refresh
Enter the security code :
No spaces, case-sensitive