Two 6.65m diameter Crossover TBMs completing the 2.8km twin running tunnels for Package 1 for the Mumbai Metro Line 3 project. The hybrid-type rock/soft ground single shield machines have completed the first two of their three drives through challenging mixed ground conditions of basalt rock with transition zones of shale, tuff, and breccia, taking about 90 production days to complete the 499m and 482m drives from Vidhan Bhavan Station to Churchgate Station (Fig 1).
Package 1 of the Line 3 project between Cuffe Parade Station and Hutatma Chowk Station was awarded to the Larsen & Toubro and the Shanghai Tunnel Engineering Company (L&T-STEC) JV. After delivery of the two 6.65m Robbins hybrid Crossover TBMs the first started boring in August 2018 and the second in November 2018 and broke through into Vidhan Bhavan Station in April 2019 and Churchgate Station in October 2019.
The two TBMS are working beneath a cover of 15m-20m with some structures on the surface, such as the Mittal Towers and the historic Bhikha Behram Well, have been instrumented to monitor vibrations, movements, and potential settlement.
The geology on the alignment consists of fresh greyish basalt, soft volcanic tuffs, shale, and breccias, which are consolidated rocks of angular fragments of disintegrated volcanic rock, and the tunnels transition between rock formations several times presenting:
As expected, significant amounts of groundwater with up to 300 litres/min have been encountered between Cuffe Parade and Vidhan Bhavan. Water pressures of up to 2 bar are foreseen. The expected geology and the presence of ground water required the use of a TBM with the ability to excavate effectively in continuously changing conditions.
Optimised for abrasive rock geology using a robust cutterhead mounted with disc cutters and a reinforced screw conveyor at the centerline, the hybrid XRE Crossover machines can operate in open, closed and semi-closed mode using features designed to advance in soft ground with water inflows. Dual ratio gearboxes adjust cutterhead speed and torque to the geological conditions encountered and the , screw conveyors and their bulkhead gates and discharge gates control muck extraction from the excavation chamber, while conditioning with foam and polymers and probe drills for pre-excavation grouting assist TBM operations.
Table 1: XRE Crossover TBM specifications | |||||||
Bore diameter | 6650mm | ||||||
Tunnel lining | 5 segments plus a key | ||||||
Tunnel curve | Turn radius 200m | ||||||
Ground water pressure | TBM designed for 3 bar of external water pre | ||||||
Cutterhead | • 8 variable freq. drive motors, 210 kW each • Speed: • 0-8.8rpm in hard rock mode (high speed) • 0-4.5rpm in soft ground mode (high torque) • 42 x 17” disc cutters |
||||||
Hydraulic system | • Installed power: 420 kW • Working pressure: 345 bar |
||||||
Screw conveyor | • Speed: 0-19 rpm • Torque: 100 kNm |
||||||
Segment erector | • Radio controlled • Mechanical pickup |
||||||
Ground conditioning | Foam injection via nozzles in the cutterhead and in the screw conveyor | ||||||
Ground exploration | Probe drill mounted on segment erector ring |
The two-speed gearboxes installed on the eight drive motors on the TBMs allow for a quick adaptation of the cutterhead torque and speed to the type of ground. The high speed ratio is used in full faces of hard rock, with the high torque ratio, which increases the available torque by a factor of 2.5, allow for operation in soft or mixed face conditions. The extra torque is required to start the cutterhead should there be a face collapse, or to advance when the cutterhead is full of excavated material.
The cutterhead design is optimised for hard rock with six peripheral bidirectional muck buckets. In extreme soft and running ground conditions, the opening ratio of the cutterhead can be increased by removing part of the face plates and installing soft ground cutting tools. The roll angle of the TBM is maintained by alternating the direction of cutterhead rotation at each TBM stroke. This allows for a simpler thrust system, eliminating the need for a skew ring. As in an EPB machine, maintenance intervention into the excavation chamber is via a manlock with hyperbaric interventions at up to 3 bar when necessary in high water ingress conditions. All cutters are replaceable from the cutterhead chamber.
A screw conveyor in the centre of the XRE Crossover TBM offer several advantages over both traditional hard rock and EPBM designs:
Due to the geology being primarily rock, extra wear protection was added to the screw conveyor and the conveyor includes a replaceable casing liner, replaceable flight plates, and extra access doors in the casing for maintenance and replacement of the wear plates.
|
| ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||
A major advantage of the centre screw and peripheral muck buckets is a substantial reduction in wear to cutter tools compared to an EPBM boring in rock. This is especially the case when an EPBM is operating in open mode, due to the inefficiency of the standard inclined screw conveyor. The amount of excavated material in the lower chamber of an EPBM feeding the screw also subjects the cutting tools and cutterhead constantly to a re-grind wear action. An average of almost 600m3 of rock cut per cutter is an impressive statistic when assessing basic cutter costs. From an operational point of view, 17 linear meters of boring per cutter reduced the frequency of interventions to an average 54m of boring.
The TBMs are equipped with a foam plant feeding six injection nozzles on the cutterhead and one at the inlet of the screw conveyor. Foam fulfils several tasks to:
A probe drill can be installed on the erector ring for ground mapping ahead of the excavation. Drilling is through 12 ports around the TBM shield at a 7-degree angle from the TBM axis and through six ports straight forward through the cutterhead. Probe holes can be used in an umbrella pattern for pre-excavation grouting to consolidate and seal the ground in front of the cutterhead to permit higher boring rates. Several lubrication ports are installed radially along the TBM shield for injection of bentonite to reduce friction in sticky conditions or squeezing ground.
The term hybrid machine has been used in the industry for some time. However, the term has often been applied to machines that require lengthy operations to change the screw conveyer for a belt conveyor to perform efficiently in different ground conditions. We now have a generation of machines that are truly hybrid, which can change from rock mode to soft ground mode almost instantly.
|
|