Pre-bid reports prepared for contractors preceded the advent of GBRs.
Independent geotechnical consultants have prepared these (pre-bid) reports for the last 70 years or more. I personally have prepared them for the past 40 years and find no conundrum in defining a baseline. We have also successfully defended the contractor’s differing site condition claims using our pre-bid reports. We relied on given physical properties, considered the contractor’s anticipated use of means, methods and equipment, and provided an experience-based expectation of progress.
The GBR should be limited to physical facts and cautionary statements, leaving interpretation up to the contractor or his consultant. If the engineer does not trust the contractor’s assessment, it should require a specialist to interpret the data. The problem of the perceived baseline conundrum is a result of the limited education, ability, and construction-specific experience of the person drafting the GBR.
Furthermore, I have often seen reports that are nebulous in order to avoid conveying specific information. Disclaimers have even crept into GBRs, which dilutes responsibility! Many large engineering firms have managed to undermine the concept. Ask the silent majority if you wish to have a clearer perspective that leads to neutralizing the conundrum.
Since their first use in the mid 1970s, after some stellar claims for several notable tunneling projects in the United States, and the work of the groups like the United States National Committee on Tunneling Technology, some enlightened owners such as the Washington Area Metropolitan Transit Authority with its multiple modern underground mass transportation tunneling projects for the subways in the nation’s capital, and others led to a steady development over the ensuing years in to what is now generally called Geotechnical Baseline Reports (GBR).
The goal of baselines is to provide contractually binding and meaningful descriptions of geotechnical conditions to be encountered during tunnel construction. The objectives for establishing the baselines aim at:
Taken with the other contracting reforms, including Geotechnical Data Reports (GDR) and Disputes Review Boards (DRBs) of this same time period, the objective was to improve contracting practice and minimize claims and disputes, as well as providing a means of settling disputes and claims on the job without costly and time consuming litigation which had pervaded the underground construction industry. These claims, and costly and lengthy litigations had lead to disenchantment for underground construction and generally a “bad rap” for the industry.
The conundrum today for the geotechnical professional, tasked with writing the GBR, as to what is to be baselined, if indeed baselined or not.
Consideration must be given to several aspects:
Generally as applied today,
The task then for the GDR preparation, is how best to describe the exiting conditions and how they may mesh with contractual provisions or other regulatory requirements, such as, for example, gassy or potentially gassy ground, and how are they provided for in the contract.
Just as importantly, what are the Owners needs and tolerances and understanding of the baseline?
With these things to consider the choice to baseline may not be as clear cut as it would appear, nor a simple engineering decision.
These few steps are offered to try to answer the question and provide guide the development of the baselines.
All this being said there is the assumption that good engineering judgment will be executed and that the needs and requirements of the Owner will be observed. The ASCE’s Underground Technology Research Council’s Geotechnical Baseline Reports for Construction, provides a detailed and respected description and application of Baseline Reports which has been updated several times to keep up to current practice.
At all times it must be remembered that GBRs are not a panacea and do not by themselves guarantee a successful project. Difficult and complex ground conditions require an experienced, qualified, and conscientious Contractor, whose selected means and methods are appropriate and compatible with the anticipated ground conditions in addition to a complete GBR and good engineering design.
Debunking the baseline conundrum Dec 2015
Dr. Peter J. Tarkoy, USA
Pre-bid reports prepared for contractors preceded the advent of GBRs.
Independent geotechnical consultants have prepared these (pre-bid) reports for the last 70 years or more. I personally have prepared them for the past 40 years and find no conundrum in defining a baseline. We have also successfully defended the contractor’s differing site condition claims using our pre-bid reports. We relied on given physical properties, considered the contractor’s anticipated use of means, methods and equipment, and provided an experience-based expectation of progress.
The GBR should be limited to physical facts and cautionary statements, leaving interpretation up to the contractor or his consultant. If the engineer does not trust the contractor’s assessment, it should require a specialist to interpret the data. The problem of the perceived baseline conundrum is a result of the limited education, ability, and construction-specific experience of the person drafting the GBR.
Furthermore, I have often seen reports that are nebulous in order to avoid conveying specific information. Disclaimers have even crept into GBRs, which dilutes responsibility! Many large engineering firms have managed to undermine the concept. Ask the silent majority if you wish to have a clearer perspective that leads to neutralizing the conundrum.
With regards,
Dr. Peter J. Tarkoy, USA
|
|